Bitdeer July self-mining hashrate climbs 35% to 22.3 EH/s, mined 282 Bitcoin

Published 2 months ago Positive
Bitdeer July self-mining hashrate climbs 35% to 22.3 EH/s, mined 282 Bitcoin
Auto
Bitdeer (BTDR) reported 282 bitcoin mined in July, a 39% increase from June, as continued SEALMINER deployments lifted self-mining hashrate 35% to 22.3 EH/s. Total hashrate under management reached 36.4 EH/s, including 13.9 EH/s from hosting customers. Management reiterated its goal of reaching 40 EH/s of self-mining capacity by the end of October. Bitdeer held 1,667 bitcoin at month-end.

The company energized a 100 MW hydro-cooling conversion at its Rockdale, Texas facility and brought online a combined 159 MW at Tydal, Norway and Jigmeling, Bhutan, bringing total available capacity to 1,257 MW. In Massillon, Ohio, initial energization is now targeted for the end of October, with the full timeline pushed to late Q1 2026.

Enjoying the read? Get our newsletter directly to your inbox on all things Bitcoin-equities by clicking here.

Bitdeer’s manufacturing arm had produced 21.2 EH/s of SEALMINER A2 rigs by the end of July, with 10.2 EH/s deployed for self-mining, 5.9 EH/s shipped to customers, 4.8 EH/s in transit, and 0.3 EH/s preparing to ship. The SEALMINER A3 is scheduled to launch in September, and the next-generation SEAL04 chip (A4) is targeting efficiency of about 5 J/TH.

The company also reported near-full utilization of its NVIDIA DGX SuperPOD GPU cloud services, with deployment of NVL72 GB200 units on track for Q3 and GB300 systems under evaluation.

Read More:

Cango sees 45% surge in July bitcoin production, hashrate expands to 50 EH/s IREN mines 728 Bitcoin in July, reports $65.6 million in profit

At time of publication, BTDR is up 1%  from yesterday’s close.